Run@Rate Capacity Verification: How to Prove Production Capacity

What is Run@Rate?

Run@Rate (capacity verification) is a key step in PPAP and customer capacity requirements: the supplier runs production continuously under mass-production conditions at the customer required takt and verifies that the line can stably achieve the target capacity. It usually runs in parallel with PPAP initial sample approval and is hard evidence that you can not only make samples but also deliver volume stably. The verification record is core evidence for customer audits of capacity commitments and the basis of ramp-up planning.

What Indicators Are Verified?

The tool guides you to record three data groups: output (shift quantity and good parts), takt (actual takt, target takt and bottleneck station takt) and losses (planned downtime, changeover, breakdowns, waiting and quality loss time). It also records staffing and shift arrangements during verification so real production conditions are reproduced and results are repeatable. It automatically calculates availability, performance efficiency, quality rate and overall equipment effectiveness (OEE) and compares them with the target takt to judge whether the line meets requirements.

How Is Pass or Fail Decided?

The judgment has three steps: whether the takt meets the customer required takt including necessary margin (an actual takt about 10% better than required is generally advised), whether OEE reaches the target (85% or more is commonly considered good), and whether continuous running is stable without frequent stops or batch defects. The tool outputs a capacity table and gap analysis, pointing unresolved items directly to bottleneck stations and loss causes, and ranks improvement priorities so the biggest downtime losses come first.

Step-by-Step Usage

Enter the target takt and shift time, record output, downtime and defects along the timeline, let the tool compute OEE and shift capacity, and export a verification report as a PPAP attachment. Before verification, use a VSM value stream map to review the line and SMED to eliminate changeover losses, then verify the improved actual capacity with this tool. Submit the report with PPAP and the control plan to the customer, and archive it as the production capacity baseline and the comparison point for future capacity improvements.

Open Run@Rate Capacity Verification → Calculate online in your browser · free registration · PC and mobile
AUTOMOTIVE Discussions · Latest
No discussions yet — be the first to ask a question in the community.
Frequently Asked Questions
How long should a Run@Rate run?
Usually the customer specifies a number of shifts or continuous production hours (for example three consecutive shifts). The key is covering normal production conditions, including changeover and breaks.
What OEE should be achieved?
World-class is about 85%, and customers may demand more. The point is proving stable output at the required takt, not chasing an absolute high score.
What if capacity is not met?
Use loss analysis to locate the bottleneck (equipment breakdown, changeover, waiting, defects), improve with SMED, TPM and line balancing, then re-verify.
Must verification data be submitted to the customer?
Customers usually require the Run@Rate report in PPAP or the capacity agreement as proof of the capacity commitment.